Broad Channel Athletic Club Case Study | Storm Recovery

September 30, 2020

Project Specs:

  • Location: Broad Channel - Queens, NY
  • Certified Installer: FSR
  • Engineer of Record (EOR): H2M Architect + Engineers
  • Geotechnical Engineer: YU & Associates
  • Helical Piles Specifications: - 24 MacLean Power Systems (MPS) Helical Piles - D10 (1.75" Round Corner Square) Lead w/ 8", 10", 12" Dia. Helices on a 7' Shaft & P35 (3.50" x 0.216" Pipe Shaft) Extensions - Average Depth of Helical Piles: 56' - Minimum Req'd Torque of Helical Piles: 5,000 ft-lbs
  • Ultimate Load(s): - 50 kips (Compression)

The Broad Channel Athletic Club (BCAC) is the largest youth sports organization in Queens, NY. In the aftermath of Super Storm Sandy, the BCAC was ravaged by floodwater and its facilities were in disrepair. As a part of the NY Rising Community Reconstruction Program developed by governor Andrew Cuomo, the BCAC was required to build a new two-story storage building for all of the sporting equipment that was going to be used by the club and the neighboring American Legion.

The results of YU & Associates boring tests determined that the soil at the BCAC was made up mostly of organic material and weak clays. This is a typical feature of the island neighborhood of Broad Channel. With this information, H2M Architect + Engineers designed the new two-story storage building with a deep foundation system using MacLean Power Systems helical piles.

The Helical Pile Installation

FSR was contracted to install 24 1.75” round corner square (RCS) shaft helical piles, however, when tested in the field, they were not performing as expected. FSR worked with the engineers at H2M to develop a solution using a different configuration. The redesigned MPS helical pile using 1.75” RCS leads with 3.50” pipe shaft were then installed to 56 feet to bypass the multitude of unsuitable layers of soil and performed as designed by the engineer. Each of the helical piles was installed to a minimum torque of 5,000 ft-lbs to resist settling and any potential uplift by future storm surges.

Premium Technical on site installing helical piles for new construction
close up of drilling into ground
worker adjusting drill
helical pile installation site
Storm Recovery sign, from the New York Governor's office

Request Your Free Quote

"*" indicates required fields

This field is for validation purposes and should be left unchanged.

All Fields Are Required

Premium Technical Services Reviews

Honest Reviews from Customers Just Like You
Copyright © 2026 Premium Technical Services | All Rights Reserved
 | Privacy Policy | Terms & Conditions | Sitemap
cross-circle